|
 |
Draft building & construction contracts, dispute resolution &
litigation... |

|
|
|
|
|
Building
disputes: Experienced construction
lawyers advising clients on draft contracts, alternative
dispute resolution and litigation
|
|
Solicitors here
advise on and conduct claims in relation to building and construction
work. Our solicitors also draft building contract documentation.
|
|
FIXED
CHARGE PACKAGE WITH OPTIONS & RECOMMENDATIONS
|
|
|
Our
Building and Construction Disputes Unit has substantial experience in
advising on and conducting claims arising out of building and
construction work.
We advise and
represent in legal proceedings UK and international clients in building
and construction disputes throughout England and Wales.
 |
 |
 |
| |
“Repudiation in the context of this case is taken to describe
the circumstances where “one party so acts or expresses himself as to
show that he does not mean to accept the obligations of a contract any
further” – see Heyman v Darwins
[1942] AC 356 at 361 per Lord Simon.
In normal circumstances a breach of contract by one party does not
entitle the other party to bring the contract to an end. There are two
exceptions to this rule:
(1) where the contracting parties have agreed whether by
express words or by implication of law that any (or a particular)
breach of contract shall bring the contract to an end;
(2)
where the event resulting from the breach of contract
has the effect of depriving the other party of substantially the
whole benefit which it was the intention of the parties that it
should obtain from the contract, i.e. where there is a fundamental breach – see
Lord Diplock in Photo
Products v Securicor [1980] AC 827
at 849.
In the second
case the court must consider the commercial significance of the breach
or breaches of contract. To amount to a fundamental breach it must go
to the root of the contract - see Federal
Commerce v Molena Alpha [1997] AC 757 at 779.
Repudiation
requires acceptance if it is to bring the contract to an end. Failure
to continue
to perform may be sufficient notice that the innocent party has elected
to treat the contract as at an end. See Lord Steyn in Vitol SA v Norelf Ltd [1996] AC
800 at 810/811.
In general, mere negligent omissions or bad workmanship,
where the work is substantially completed, does not go to the
root of the contract and is not therefore repudiation - see Hoenig v Isaacs [1952] 2 All ER
176.
However,
an accumulation of breaches may indicate an inability on the part of a
contractor to deliver the contract to a reasonable standard. In Sutcliffe v Chippendale & Edmonson
[1971] 18 BLR 157 at 161 the court held that:
“the
contractors’ manifest inability to comply with the completion date
requirements, the nature and number of complaints from sub-contractors
and [the architect’s] own admission
that in May and June the quality of work was deteriorating and the
number of defects was multiplying, many of which he had tried
unsuccessfully to have put right, all point to the truth of the
complainant’s expressed view that the contractors had neither the
ability, competence or the will by this time to complete the work in
the manner required by the contract”.
Where time
is not of the essence, delay on the part of the contractor does not
amount to a repudiation unless it is shown that he cannot complete the
contract within a reasonable time or that the delay is such as to
deprive the innocent party of substantially the whole benefit of the
contract.
In Felton v Wharrie (1906) HBC, Vol 2,
398, the contractor had not finished the work by the completion date
and when asked how long it would take he said he could not say. The
contractor continued to work on site and two weeks later he was
forcibly ejected. The Court of Appeal held that the employer had no
right to determine the contract.
“If he were
going to act upon the claimant’s conduct as being evidence of his not
going on, he ought to have told him of it and to have said, ‘I treat
that as a refusal’, and the man would know of it but the fact of
allowing him to go on cannot be any evidence of justification of
re-entry.”
“As far as the employer is concerned,
if the employer wrongfully and by his own act and without lawful excuse
renders completion of the contract impossible, that amounts to a
repudiation. This must apply to the situation where the employer ejects
the contractor from site before completion.” Hayes & Others –v- Gallant [2008]
|
|
 |
 |
|
|
|
|
|
We understand that, irrespective of the
amount of money involved, building disputes can rapidly become
stressful, time-consuming and expensive.
|
|
Accordingly, we
aim to equip our clients, whether claiming, defending and/or
counter-claiming, with a tailored professional analysis of their actual
legal position at an early stage, often by way of an affordable
fixed-fee package.
|
 |
 |
 |
| |
Frequent
issues
Issues our clients raise and on which
we advise include:
- Remedial works
are required.
- The work has not
been completed on time.
- I have been
overcharged for the work undertaken.
- What happens if
there wasn't a written contract.
- I would like to
get my money back.
|
|
 |
 |
 |
|
|
|
|
 |
 |
 |
| |
Dispute resolution
It is our experience that many building
disputes can be
resolved without recourse to the legal process.
In view of this we
seek to open lines of communication between the parties at an early
stage and to explore the possibility of attempting to resolve the
dispute by way of alternative dispute resolution including:
- round-table meetings
between the parties;
- mediation;
- arbitration;
- adjudication
- preparation and
exchange of experts
reports;
- meetings of experts.
|
|
 |
 |
 |
We find
that alternative dispute resolution often proves a cost-effective and
efficient means of resolving disputes without the need to commence
court proceedings.
If early
dispute-resolution does not prove possible our
lawyers know how to be effective, tenacious litigators.
We have
wide experience of representing clients in arbitrations and in
litigation in the County Courts, High Court, Technology and
Construction Court and Mercantile Court.
|
|
|
|
Be
prepared
None of us conducts our
affairs with litigation in mind, but when a dispute arises, keeping
these practical steps in mind may be of assistance:
|
|
Put
it in writing - even if there
has been little or no written correspondence between you and the
builder beforehand, you should put your grievances in writing and give
the builder a chance to respond. This may assist in showing that your
actions were reasonable if the matter ever comes before a court.
|
|
Make
contemporaneous notes - or
those things that cannot be recorded in writing this may be the best
alternative. For example if you consider that the builder is behaving
in an unreasonable manner or that aspects of the work/working practices
are unsatisfactory, record what/where/when/who while your recollection
is fresh.
|
|
Keep
receipts and invoices - this
may sound obvious but if the dispute is in relation to amounts claimed
or the cost of remedial work, accurate details of the amounts involved
will be essential. Similarly, if further work is required obtain a
fully itemised quotation/estimate in relation to the work.
|
|
Take
photographs - this may be of
assistance in showing defective work or the stage the work has reached.
It may be particularly important to show the position the work has
reached if subsequent work/alteration are likely to take place.
Ultimately, however, it is likely that if the dispute progresses expert
evidence will be required and contemporaneous photographs may be of
assistance to experts.
|
|
Try
to be calm and collected -
this may go some way to taking the "heat" out of the dispute and
avoiding the breakdown of your working relationship.
|
 |
 |
 |
| |
Seek
professional advice:
-
Residential building disputes
-
Commercial building disputes
-
Litigation
-
Mediation
-
Arbitration
-
Advice on forms of building contract
-
Adjudication
|
|
 |
 |
|
|
FIXED
CHARGE PACKAGE WITH OPTIONS & RECOMMENDATIONS
|
|
E-mail us with details of your
enquiry on building@humphreys.co.uk
Include your telephone number,
fax number and address. |
Tel (0117) (international +44
117) 929 2662
Fax (0117) (international +44 117) 929 2722 |
|

|
 |
Relevant Material
|
 |
|